Knik Goose Bay Road MP

16

Knik Goose Bay Road MP 14.7 6/4/22 7 p.m. UPDATE: We had to bring in additional material this afternoon, which took some extra time. Crews are finishing up embankment, and structural section and then paving. We anticipate reopening Sunday morning.

6/4/22 8 a.m. UPDATE: Crews worked on the Southbound lanes until 3 am. Replacement crew started on Northbound lanes early this morning. We are anticipating reopening the road to traffic late tonight. Will post updates as they become available.

6/3/22 11:51 p.m. UPDATE: Construction crews are still working on the pipe failure. They will reopen the road once repairs are complete. Thank you for your continued patience.

Original source can be found here.

ORGANIZATIONS IN THIS STORY

!RECEIVE ALERTS

The next time we write about any of these orgs, we’ll email you a link to the story. You may edit your settings or unsubscribe at any time.
Sign-up

DONATE

Help support the Metric Media Foundation's mission to restore community based news.
Donate

MORE NEWS